Western Part Of Jamal Abdul Nasser Road Intersection Complete 65 Percent

13 February 2017 Information

The Ministry of Public Works’ assistant undersecretary for road engineering affairs Ahmed AlHassan said 65 percent of the western part of Jamal Abdul-Nasser Road’s intersection is complete. He added that two bridges will open in March and a third will open in April. Hassan also noted that the project will be concluded by June 2018 at a total cost of KD 34.9 million.

 

SOURCE : IIK